Priced bill of quantities
A bill of quantities is a document prepared by the client's cost consultant that provides measured quantities of the items of work necessary to construct a development. These items of work are described by the drawings and specifications in the tender documentation. The quantities may be measured in number, length, area, volume, weight or time.
An unpriced bill of quantities (sometimes referred to as the tender pricing document) is issued to tenderers, who will then estimate their price for each item. This priced bill of quantities constitutes the tenderer's complete offer. It is the unpriced bill of quantities, but with the tenderer’s rates, costs and totals added.
The preparation, by the client’s consultants, of an unpriced bill of quantities assists tenderers in the calculation of construction costs for their tender, and, as it means all tendering contractors will be pricing the same quantities (rather than taking-off quantities from the drawings and specifications themselves), it provides a fair and accurate system for tendering. It also makes it possible to compare both the overall price and individual items directly with other tenderers’ offers, allowing a detailed assessment of which aspects of a tender may offer good or poor value. This information can assist with tender negotiations.
The priced bill of quantities will also:
- Assist with the agreement of the contract sum with the successful tenderer.
- Provide a schedule of rates assisting with the valuation of variations.
- Provide a basis for the valuation of interim payments.
- Provide a basis for the preparation of the final account.
It is very important that bills of quantities are prepared according to a standard, widely recognised methodology. This helps avoid any ambiguities or misunderstandings and so helps avoid disputes arising through different interpretations of what has been priced. In the UK, bills of quantities for general construction works will most commonly be prepared in accordance with the Standard Method of Measurement 7th Edition (SMM7) or the New Rules of Measurement, which became operative on 1 January 2013 and replaced SMM7 on 1st July 2013.
Bills of quantities are most useful to the contractor when they are prepared in work sections that reflect likely sub-contract packages. This makes it easier for the contractor to obtain prices from sub-contractors and is more likely to result in an accurate and competitive price.
[edit] Related articles on Designing Buildings Wiki
- Bill of quantities.
- Common arrangement of work sections.
- Common mistakes in bill of quantities.
- Comparison of SMM7 with NRM2.
- New Rules of Measurement.
- Schedule of rates.
- Schedule of work.
- Standard Method of Measurement.
- Tender documentation.
- Tender pricing document.
- Types of bill of quantities.
- Unpriced bill.
Featured articles and news
Retrofit 25 – What's Stopping Us?
Exhibition Opens at The Building Centre.
Types of work to existing buildings
A simple circular economy wiki breakdown with further links.
A threat to the creativity that makes London special.
How can digital twins boost profitability within construction?
The smart construction dashboard, as-built data and site changes forming an accurate digital twin.
Unlocking surplus public defence land and more to speed up the delivery of housing.
The Planning and Infrastructure Bill
An outline of the bill with a mix of reactions on potential impacts from IHBC, CIEEM, CIC, ACE and EIC.
Farnborough College Unveils its Half-house for Sustainable Construction Training.
Spring Statement 2025 with reactions from industry
Confirming previously announced funding, and welfare changes amid adjusted growth forecast.
Scottish Government responds to Grenfell report
As fund for unsafe cladding assessments is launched.
CLC and BSR process map for HRB approvals
One of the initial outputs of their weekly BSR meetings.
Architects Academy at an insulation manufacturing facility
Programme of technical engagement for aspiring designers.
Building Safety Levy technical consultation response
Details of the planned levy now due in 2026.
Great British Energy install solar on school and NHS sites
200 schools and 200 NHS sites to get solar systems, as first project of the newly formed government initiative.
600 million for 60,000 more skilled construction workers
Announced by Treasury ahead of the Spring Statement.
The restoration of the novelist’s birthplace in Eastwood.
Life Critical Fire Safety External Wall System LCFS EWS
Breaking down what is meant by this now often used term.
PAC report on the Remediation of Dangerous Cladding
Recommendations on workforce, transparency, support, insurance, funding, fraud and mismanagement.
New towns, expanded settlements and housing delivery
Modular inquiry asks if new towns and expanded settlements are an effective means of delivering housing.